Invoices are the bills you receive from subcontractors and suppliers. Each vendor invoice is tied to a commitment (a subcontract or purchase order) and billed against its lines, so you never pay more than what was committed plus approved changes.

Process a vendor invoice

1

Create the invoice

Go to Financial Control → Invoices, click New Invoice, and select the commitment being billed.
2

Enter billed amounts per line

For each commitment line, enter this period’s billed amount. Syntecton shows scheduled value, previously billed, and remaining so you can validate the request.
3

Apply retention

Retention is calculated per the commitment terms. Confirm the retained amount and net payable.
4

Attach backup and route for approval

Attach the vendor’s invoice document and lien waiver, then submit for approval per the project workflow.

Troubleshooting

“Exceeds remaining commitment”

The billed amount is more than the line’s remaining value. Either reduce the amount or process a commitment change order first to increase the line.